Durations

J

Jack

How can I can the existing durations in my project from
days to hours? I have tried tools, options, schedule, and
changed the Duration is entered in days to hours. This
only takes place from the time it is changed forward.
Thanks
 
J

JackD

Tools menu / macros/ find the format duration macro / run it and follow
prompts.

-Jack
 
R

Rod Gill

Hi,

Tools, Macro, Macros and run the macro Format_Duration. You may need to set
macro security to medium to allow the macro to run.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 