R
Ric Deez
Hi there,
Is there a way of defining a task name so that it is dependent on other
custom and standard fields that exist in the project plan? Example:
Name Task Name Text30 Text29
Wangaratta Tier 2 POP Commissioning Wangaratta 3
- Installation of PSTN lines ( x 3) Wangaratta 3
- Task 2 Wangaratta 3
- Task 3 Wangaratta 3
<<POPx> Tier 2 POP Commissioning <<POPx>>
- Installation of PSTN lines ( x <<PSTN_line_no>> <<POPx>>
<<PSTN_line_no>>
- Task 2
- Task 3
is it possible to have task names defined as = [name] & " " & [text30] for
one ROW and defined as = [name] & "( x " & [text31] & ")" for another ROW?
I know about doing the customise fields and formula to change all of the
fields on a specific COLUMN but I don't know how to define it on a row by
row basis. Is this possible?
Regards,
R.
Is there a way of defining a task name so that it is dependent on other
custom and standard fields that exist in the project plan? Example:
Name Task Name Text30 Text29
Wangaratta Tier 2 POP Commissioning Wangaratta 3
- Installation of PSTN lines ( x 3) Wangaratta 3
- Task 2 Wangaratta 3
- Task 3 Wangaratta 3
<<POPx> Tier 2 POP Commissioning <<POPx>>
- Installation of PSTN lines ( x <<PSTN_line_no>> <<POPx>>
<<PSTN_line_no>>
- Task 2
- Task 3
is it possible to have task names defined as = [name] & " " & [text30] for
one ROW and defined as = [name] & "( x " & [text31] & ")" for another ROW?
I know about doing the customise fields and formula to change all of the
fields on a specific COLUMN but I don't know how to define it on a row by
row basis. Is this possible?
Regards,
R.