B
Brian C
In MS Project, the formula for EAC is ACWP + (Baseline cost/CPI). Where I
work, we use Baseline 1 to be the current Baseline. I have set the Earned
Value Calculation to use Baseline1, but I am unable to find anything that
confirms the EAC is using Baseline1 Cost.
Question: does the EAC caluclation always use baseline cost or does it
follow the Earned Value setting stating which baseline values to use for EV
calculations?
work, we use Baseline 1 to be the current Baseline. I have set the Earned
Value Calculation to use Baseline1, but I am unable to find anything that
confirms the EAC is using Baseline1 Cost.
Question: does the EAC caluclation always use baseline cost or does it
follow the Earned Value setting stating which baseline values to use for EV
calculations?