Early Task Completion

D

David

So, say that I originally scheduled a task to start on 12/1 and complete
12/5, so my baseline start and complete dates are those dates.

What if I complete this task early and the actual start is 11/1 and actual
complete 11/5.

If I set my status date to 11/9, my SPI value would be incorrect, saying it
was 0.
SPI = BCWP/BCWS. So even if I am ahead of schedule, the spi value is
showing me as behind schedule? It should really be greater than 1.

Is this a known problem of Project Pro? Or is there a solution to this?

David
 