Earn value - issue with calculation

A

alex

Hi,
The last week I posted a post about this point but the point is still opened.
So I continu to investigate and put update. (thanks Julie).

Context:
Be sure the data (earn value) are correct before to propose to project
manager.

Issue:

I find several informations on office online and other place.

To clarify the fields:

"Travail réel" is equal to actual work.
"Coût rée" is equal to actual cost.
"Coût" is equal to cost.
"Travail planifié" is equal to baseline work.

So I analyse line after line for the first column, but the value obtains for
EV is incorrect.
What is your point of view?

You can find the entire document below.
http://docs.google.com/Doc?id=dgq4sw2r_2072t6k76z34

best regards,
Alexandre BARAULT
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top