I have a small schedule that has resource assignments, has been baselined and
actuals have been entered. When I look at Project pro 2007 EV view all the
info shows up. The problem is when the OLAP cube is built, with no errors,
the ACWP has values but the BCWP and BCWS are 0.
Any ideas on why this would happen and even better how do you correct it.