Y
Yazz
I am in desperate need of help as there is a slight deadline this afternoon.
I have set a baseline, and after sometime set another baseline (baseline2)
due to some significant variations to the project.
When I run an earned value report, the BAC, VAC, and I presume EAC is based
on the original Baseline, NOT baseline2. I have set in
Options->Calculations->earned value the settings to calculate earned value on
baseline2.
I am also using Physical % Complete as the measure for earned value
(specified at project option level and at task level as well).
I want to get a report comparing the current actuals to baseline2. I
thought it would be as easy as running an earned value report in Project
2003, but Im very stuck and a deadline is approaching.
Anyones help would be great!!
A second part question is that EAC is different when the project is run on
2003 and when run on 2007. Does Project use different formulas for EAC in the
different versions?
Cheers,
Yazz
I have set a baseline, and after sometime set another baseline (baseline2)
due to some significant variations to the project.
When I run an earned value report, the BAC, VAC, and I presume EAC is based
on the original Baseline, NOT baseline2. I have set in
Options->Calculations->earned value the settings to calculate earned value on
baseline2.
I am also using Physical % Complete as the measure for earned value
(specified at project option level and at task level as well).
I want to get a report comparing the current actuals to baseline2. I
thought it would be as easy as running an earned value report in Project
2003, but Im very stuck and a deadline is approaching.
Anyones help would be great!!
A second part question is that EAC is different when the project is run on
2003 and when run on 2007. Does Project use different formulas for EAC in the
different versions?
Cheers,
Yazz