I am working with a Project Professional / Server 2003 environment and there
seems to be some inconsistencies with the way Project Professional is
currently calculating earned value against some of the published plans,
however it does seem to be working as expected in several others.
When opening a published plan in Project Professional, in some circumstances
where tasks are definately baselined and actuals are recorded against them,
within the Task Usage view - the BCWP (ACWP and BCWS also) is not being
calculated? Earned value method is "% Physical Work Complete" and is
associated with the correct baseline under "Tools > Options > Calculations"
etc. Also, the Enterprise resources assigned to tasks within the plan have
been set with nominal $1/hr standard & overtime rates.
If anyone has experienced this issue before and can shed any light on the
matter, I would greatly appreciate it.
Thanks in advance,
Darren
seems to be some inconsistencies with the way Project Professional is
currently calculating earned value against some of the published plans,
however it does seem to be working as expected in several others.
When opening a published plan in Project Professional, in some circumstances
where tasks are definately baselined and actuals are recorded against them,
within the Task Usage view - the BCWP (ACWP and BCWS also) is not being
calculated? Earned value method is "% Physical Work Complete" and is
associated with the correct baseline under "Tools > Options > Calculations"
etc. Also, the Enterprise resources assigned to tasks within the plan have
been set with nominal $1/hr standard & overtime rates.
If anyone has experienced this issue before and can shed any light on the
matter, I would greatly appreciate it.
Thanks in advance,
Darren