Hello,
I understand that you entered some actuals then you baselined the plan. That
the reverse order of the normal way...
I'm afraid you have to remove all the Actuals (% complete = 0), set back all
the data as at the begining of the project, then Save the baseline.
Now you can re-entered all Actual data.
I hope that you were not too advanced in the project progress.... ;-(
Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris
SR said:
I created a new plan and have actuals and baselined the project before
tracking actuals against. However I do not get any Earned Value
Calculations. There is a fixed hourly rate for the resources and it does
calculate the SV and PV but shows 0.00 on the EV and thus 0 on the CPI and
SPI. Any help is appreciated.