G
gb
I just set up my data for Earned Value (using % Complete), loading Standard
Rates, establishing a baseline for the .mpp, scheduled Work hours, and have
team members entering actual hours to My Tasks through Project Server 2007.
However, starting at week 23 in my .mpp, the BCWS is $0.00. Additionally, I
have adjusted the status date from "NA" to a date in the recent past, but
still no BCWS all the way through the .mpp.
Any suggestions?
Rates, establishing a baseline for the .mpp, scheduled Work hours, and have
team members entering actual hours to My Tasks through Project Server 2007.
However, starting at week 23 in my .mpp, the BCWS is $0.00. Additionally, I
have adjusted the status date from "NA" to a date in the recent past, but
still no BCWS all the way through the .mpp.
Any suggestions?