Earned Value & Different BCWP Numbers

N

Nikole

When comparing the BCWP in the Ganntt Chart and the Task Usage view for the
same status date, we're noticing that the dollar amounts do not match. Both
are cumulative numbers, so they should be the same, right? Can anyone shed
any light as to why these numbers are not the same?

Thanks!
 
J

Jim Aksel

I ran into a similar problem about a year ago, but it was with ACWP.
Would you be willing to send me the file so I can take a closer look? I
want to compare what you have to a bug report that I believe is still open.

Is this a 2003 or 2007 version?

send the file to jeaksel (at) yahoo (dot) com
--
If this post was helpful, please consider rating it.

Jim

Check out my new blog for more information:
http://www.msprojectblog.com
 