Can someone confirm if it is possible to switch midstream from the Earned
Value method calculated based on "% complete" to "Physical % complete"?
It seems that MS Project uses the method the file was created with to
compute BCWP. Even if you copy and paste the entire project to a blank
project file that has been created with the alternate EV method, it does NOT
allow you to change the EV method. Is this correct, or am I missing
something?