Earned Value Plot not reaching 100%

G

Guest

Does anyone know why my baseline plot never reaches 100%
eventhough all activities are included?
 
J

Jack D.

Does anyone know why my baseline plot never reaches 100%
eventhough all activities are included?

Your baseline never reaches 100% or your actual never reaches 100%?
What status date are you using?
I think you will need to supply more information in order to get a decent
answer here.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP
email: J -at- eM Vee Pee S dot COM


+++++++++++++++++++
 
G

Guest

My baseline plot never reaches 100%.

I am using a status date which is the same as the latest
task in the schedule.

Thanks,
 
G

Gérard Ducouret

Haven't you a finish milestone with any cost which has not been baselined ?

Gérard Ducouret
 