H
hadjionm
I often get summary tasks showing a schedule variance in the following
situations:
1. All the tasks below the summary are completed (and therefore can not
have a schedule variance).
2. The tasks are not completed but do not have any schedule variance
themselves.
Am I correct in assuming that the schedule variance of a summary task
must ALWAYS be the sum of its subordinate tasks?
Is there a way of 'refreshing' the earned value calculations which have
been rolled up to the summary tasks without rebaselining the subordinate
tasks?
situations:
1. All the tasks below the summary are completed (and therefore can not
have a schedule variance).
2. The tasks are not completed but do not have any schedule variance
themselves.
Am I correct in assuming that the schedule variance of a summary task
must ALWAYS be the sum of its subordinate tasks?
Is there a way of 'refreshing' the earned value calculations which have
been rolled up to the summary tasks without rebaselining the subordinate
tasks?