Please help me on this one. I'm lost on how to do this.
When I insert multiple projects from PWA to Project Pro, Project actually
inserts the projects into an "mpp" file. This is exactly what I want. The
problem comes when I go to View>Table>More Tables and use one of the Earned
Value views. The earned value CPI/SPI (at the project level) for all
projects shows as 0 even though PWA shows as 1.
How does the software actually work? And how do I get the earned value
information that I'm looking for to show up in Project Pro?
Thanks
John
When I insert multiple projects from PWA to Project Pro, Project actually
inserts the projects into an "mpp" file. This is exactly what I want. The
problem comes when I go to View>Table>More Tables and use one of the Earned
Value views. The earned value CPI/SPI (at the project level) for all
projects shows as 0 even though PWA shows as 1.
How does the software actually work? And how do I get the earned value
information that I'm looking for to show up in Project Pro?
Thanks