R
ranazarian
I am some trouble with Visual EV pivot reports coming out of MS project
My project is entered with resources and costs and I've baselined it.
All of the BCWS, BCWP, ACWP, etc fields look like they are properl
calculated in MS project. When I run the initial earned value repor
(without any actuals entered) the planned value chart looks fine. Onc
I start to enter data for actual work, however, my charts get crazy.
I've seen notes on the board about changing the level of usage data t
get it to regenerate the database and that seems to fix things but i
there something I should be doing with saving the database that woul
avoid the need to do this?
Also, I'm not sure I understand why all the numbers go to 0 after th
status date. If I set the status date out past the end of the project
everything is fine, but I can't see why the planned value should ever g
down - and that's what happens after a status date that's set in th
middle of the project. Am I missing something here
My project is entered with resources and costs and I've baselined it.
All of the BCWS, BCWP, ACWP, etc fields look like they are properl
calculated in MS project. When I run the initial earned value repor
(without any actuals entered) the planned value chart looks fine. Onc
I start to enter data for actual work, however, my charts get crazy.
I've seen notes on the board about changing the level of usage data t
get it to regenerate the database and that seems to fix things but i
there something I should be doing with saving the database that woul
avoid the need to do this?
Also, I'm not sure I understand why all the numbers go to 0 after th
status date. If I set the status date out past the end of the project
everything is fine, but I can't see why the planned value should ever g
down - and that's what happens after a status date that's set in th
middle of the project. Am I missing something here