P
pnoeric
Help-- can anyone shed some light on what seems to be an odd behavior
in MS Project? I must be using it wrong, or something.
I have three tasks (A, B, C) that follow each other (via the
'predecessor' column)-- i.e. B is dependant on A, C is dependant on B.
If I start task A on a Monday, Project shows these start and finish
dates:
Task A takes 1 day, Mon - Tues
Task B takes 1 day, Tues - Weds
Task C takes 1 day, Weds - Thu
However, if I change Task A to 2 days, I get:
Task A takes 2 days, Mon - Weds
Task B takes 1 day, Weds - Thur
Task C takes 1 day, Fri - Mon
Why does Task C now suddenly start on Friday, instead of Thursday?
Task B pushed out like it should, but that should have only rolled
task C forward one day. Very odd!
thanks,
Eric
in MS Project? I must be using it wrong, or something.
I have three tasks (A, B, C) that follow each other (via the
'predecessor' column)-- i.e. B is dependant on A, C is dependant on B.
If I start task A on a Monday, Project shows these start and finish
dates:
Task A takes 1 day, Mon - Tues
Task B takes 1 day, Tues - Weds
Task C takes 1 day, Weds - Thu
However, if I change Task A to 2 days, I get:
Task A takes 2 days, Mon - Weds
Task B takes 1 day, Weds - Thur
Task C takes 1 day, Fri - Mon
Why does Task C now suddenly start on Friday, instead of Thursday?
Task B pushed out like it should, but that should have only rolled
task C forward one day. Very odd!
thanks,
Eric