Easy way for resources to change working time

J

julie

I want to track vacation and non-available time on their individual calendars
not in administrative projects. How can resources access their individual
calendar to mark non-working time?
 
D

Dale Howard [MVP]

Julie --

They can't because there default method within Project Server to make this
happen, short of using administrative projects for this purpose. We do not
recommend the user of administrative projects to track nonworking time,
however, since their use does not cause Project Server to automatically
reschedule tasks in regular projects due to the entry of nonworking time.
Your best bet would be to establish a methodology such as the following:

1. Resource submits nonworking time request to the responsible manager
2. Responsible manager approves the nonworking time
3. Resource submits the nonworking time via e-mail to the Project Server
administrator
4. Project Server administrator enters nonworking time on resource's
calendar in Enterprise Resource Pool and adds a resource Note to document
the nonworking time

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top