edays - fixed duration - non working time on resource

C

chris.the

Hello,

today was the first time I was confronted with edays.

Now after reading a bit about it one question still remains.

If I have a task with fixed duration and edays as duration.
Does it complete ignore non-working time of assigned resources.

Because if I assign a worker with holidays he'll still have work in his
resource usage.

Thanks in advance.

Greetings,
Chris
 
G

Gérard Ducouret

Hi Chris,
Yes, a task with edays duration is running 24h/24 and 7d/7... It doesn't use
respect any resource calendar.
Generally, we don't assign human resources on such tasks, only machines...
Gérard Ducouret
 