Hello,
We are currently using 2007 version of the EPM, patched to date, Al-
Hamdulillaah (All Praises and Thanx to God Al-Mighty).
When I go to "Edit Project Properties" of a certain project and click
on "Save and Publish", after completing 100% it shows done. However,
it doesn't close automatically (i.e. I have to click on 'Close'
button) and neither does it redirects automatically to the "Proejct
Center". I have to go manually to the "Project Center" by clicking on
Home and then "Project Center".
After this, I find that my graphical indicator disappears and text is
shown "No baseline" but it was "Late" earlier. However, it always
shows "No baseline" although the project has been saved with the
baselines.
Can someone guide me on this?
Thank you
Best regards,
Tanzim Akhtar
We are currently using 2007 version of the EPM, patched to date, Al-
Hamdulillaah (All Praises and Thanx to God Al-Mighty).
When I go to "Edit Project Properties" of a certain project and click
on "Save and Publish", after completing 100% it shows done. However,
it doesn't close automatically (i.e. I have to click on 'Close'
button) and neither does it redirects automatically to the "Proejct
Center". I have to go manually to the "Project Center" by clicking on
Home and then "Project Center".
After this, I find that my graphical indicator disappears and text is
shown "No baseline" but it was "Late" earlier. However, it always
shows "No baseline" although the project has been saved with the
baselines.