D
DenverWaterPM
I have added a custom field to the timesheet view and have selected in
Customize->Published Fields "Let resources change this field" and made the
field an assignment field (we use one resource per task approach to project
scheduling).
I can see the custom field in the timesheet view but it is not editable.
I have tried all kinds of things but nothing helps. I have read the post by
Brian N who had a similar problem (7/19/2005 11:29AM) but his field became
editable. It has not done so for me.
I would be very grateful for your help.
Christine
Customize->Published Fields "Let resources change this field" and made the
field an assignment field (we use one resource per task approach to project
scheduling).
I can see the custom field in the timesheet view but it is not editable.
I have tried all kinds of things but nothing helps. I have read the post by
Brian N who had a similar problem (7/19/2005 11:29AM) but his field became
editable. It has not done so for me.
I would be very grateful for your help.
Christine