L
Lars
Hi All,
I am getting back into MSP after some time of abstinence, and I have an
issue that I can't figure out. I have a test project that I have saved with
a baseline to do some trackning exercises. In the Cost table I can edit the
"Total Cost" and "Baseline Cost" columns, which I think I should't be able
to do. At the same time I can't edit the "Actual" column, which I thougt I
should be able to....
Any clues?
Cheers
Lars
I am getting back into MSP after some time of abstinence, and I have an
issue that I can't figure out. I have a test project that I have saved with
a baseline to do some trackning exercises. In the Cost table I can edit the
"Total Cost" and "Baseline Cost" columns, which I think I should't be able
to do. At the same time I can't edit the "Actual" column, which I thougt I
should be able to....
Any clues?
Cheers
Lars