Editable tables and cells

L

Lars

Hi All,

I am getting back into MSP after some time of abstinence, and I have an
issue that I can't figure out. I have a test project that I have saved with
a baseline to do some trackning exercises. In the Cost table I can edit the
"Total Cost" and "Baseline Cost" columns, which I think I should't be able
to do. At the same time I can't edit the "Actual" column, which I thougt I
should be able to....

Any clues?

Cheers
Lars
 
R

Rob Schneider

Lars,

"Total Cost" in the cost table is actually the "Cost" field. in the
table they use the label "Total Cost" for some reason. Hover the mouse
pointer on the heading, and you can see the link to "Help on Cost" and
see there where this is is shown as a "calculated or entered" field.
Same is true for the Baseline cost which is "calculated or entered".
Read in these Help articles more about this to get your questions answered.

--rms
 
P

Projectability

Lars,

You cannot edit Actual Cost values until a task is 100% complete - Project
will calculate actual cost based upon the task % complete and the original
assigned resource cost and any fixed cost. Once a task is complete you can
enter the Actual cost to be whatever you want as opposed to what Microsoft
Project calculates the actual cost to have been.

--
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

Check the Downloads section on our Website for useful documents on both
Project Management and Microsoft Project

www.projectability.co.uk

Why not subscribe to our monthly newsletter for hints tips and views

http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFtfgVw==
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top