J
Jo
Using Project 2003...
A Team Member accidentally entered actuals on Sunday. The
Project Manager moved those hours to Monday by using the
Resource Usage view in Professional - he put 0 on Sunday
and the 4 hours on Monday, then saved and published. This
doesn't show up for the user in his timesheet view. (We do
*not* have Adjust Actuals or View Adjust Actuals allowed
in PWA.) Should this have worked? What did the Project
Manager actually do, if the changed hours aren't showing
up in PWA?
Thanks
--Jo
A Team Member accidentally entered actuals on Sunday. The
Project Manager moved those hours to Monday by using the
Resource Usage view in Professional - he put 0 on Sunday
and the 4 hours on Monday, then saved and published. This
doesn't show up for the user in his timesheet view. (We do
*not* have Adjust Actuals or View Adjust Actuals allowed
in PWA.) Should this have worked? What did the Project
Manager actually do, if the changed hours aren't showing
up in PWA?
Thanks
--Jo