Editing Actual Work Fields

L

lz3

We have set up Project Server 2003 to track progress updates by "hours
of work done per day or per week", and project plans using this update
method have had the customized fields published. Team members can
update the "Actual Work" field in the left hand side of the Timesheet
view on the Tasks page. However, a PM is asking if the "Actual Work"
field, broken down by day of the week on the right hand side of the
page, can be updated. I can find no way to open up that field for
entry. Is this possible?
Thanks
 
J

Jonathan Sofer

You must change the default tracking method in the Admin page of PWA to
hours worked per day and have the PMs republish the plans.

Or, if the administrator has not set the option to force PMs to use the
default tracking method (found on the same admin page) then each PM can
individually change the tracking method of their project by going to
Tools>Customize>Published Fields

Jonathan
 