P
Peggy Cornett
I want to edit a resource name (such as from Peggy to Peg) in the enterprise
resource pool. This resource is in multiple projects and has actual work as
well as remaining work assigned. It uses Windows Authentication. Please
confirm if the following is the best way to do edit/revise the name and what
pain I should be prepared for:
Open the resource center from within PWA
Select the resource
Choose the open icon - (NOT edit) This opens it in the checked out ent
resource pool)
Make the edit/change directly in the resource name and save.
The next time the project is opened the revised name will update
automatically.
I noticed if this change is made while the project is open, I can't save the
project because it is was checked out when I (the admin and I happened to be
the resrouce in this case too) had another name.
If I try to change this under Admin (in PWA), Users & Groups in the user
name it does not reflect the change in the resource center nor in the
Enterprise resource global pool.
Any precautions/risks?
We copy the resource name into a text field for importing into another
system. That system has a character limit of 18. However, many resource
were originally created with more than 18. We have been manually reducing
them in the text field but it would save lots of work to just go to the
source, the resource name in the enterprise pool and shorted it once and for
all. Hence, the reason for my attempt.
Peggy Cornett
resource pool. This resource is in multiple projects and has actual work as
well as remaining work assigned. It uses Windows Authentication. Please
confirm if the following is the best way to do edit/revise the name and what
pain I should be prepared for:
Open the resource center from within PWA
Select the resource
Choose the open icon - (NOT edit) This opens it in the checked out ent
resource pool)
Make the edit/change directly in the resource name and save.
The next time the project is opened the revised name will update
automatically.
I noticed if this change is made while the project is open, I can't save the
project because it is was checked out when I (the admin and I happened to be
the resrouce in this case too) had another name.
If I try to change this under Admin (in PWA), Users & Groups in the user
name it does not reflect the change in the resource center nor in the
Enterprise resource global pool.
Any precautions/risks?
We copy the resource name into a text field for importing into another
system. That system has a character limit of 18. However, many resource
were originally created with more than 18. We have been manually reducing
them in the text field but it would save lots of work to just go to the
source, the resource name in the enterprise pool and shorted it once and for
all. Hence, the reason for my attempt.
Peggy Cornett