Editing Budget Cost in PPS (Project Portfolio Server)

E

Eniola

I am trying to edit the Budget Cost for the projects in my portfoilio, but
the (blizzard) icon is not visible for some reason. What is the problem? I
will be very greatful for all help!
 
M

Marc Soester [MVP]

Hi Eniola,
i can imagine that, as part of your workflow, you have hidden this function.
I would check the workflow settings and see if you switched off the
"Editable" button for Budget once you are past a certain workflow. This could
be the reason why
hope this helps
 
E

Eniola

Mark,

Thanks for your suggestion! We do have 2 dummy workflows, but they don't
really do much (literally just 2 workflows that each contain a dummyproject
class). I looked at the Workflow Verification and Link Process Management
and saw the following Processes: Approve, Modify, Monitor, Propose Project,
Reject. Are these dafault? Could these be a cause?

Thanks again!
 
M

Marc Soester [MVP]

Hi Eniola,

yes they are defaults. Depending on how your system is set up your budget
may have various reasons why you cant see it.
Can it be your user rights?
Hope this helps
--
Marc Soester [MVP]
National Manager: EPM
http://marcsoester.blogspot.com
 
E

Eniola

Mark,

I kept playing with the workflows and it turns out you're right. Thanks so
much!
 