J
Junkyard Engineer
I know I can use multiple tasks and lag times but in this instances, I think
the split task is more appropriate but gives me hard time for editing it.
I have a task for Visiting potential customers during a project. Each visit
will be 3 days and over the project duration (14 months) there will be 14
visits, one per month. I don't want to create an activity with 14 subtasks,
it will clutter my gantt. So I splitted the task 13 times trying to leave 3
days per sub-split-task. Problem is that it's not very precise using the
mouse.
Is there a way to go back and edit the duration of all those sub-split-task
?
Thanks
the split task is more appropriate but gives me hard time for editing it.
I have a task for Visiting potential customers during a project. Each visit
will be 3 days and over the project duration (14 months) there will be 14
visits, one per month. I don't want to create an activity with 14 subtasks,
it will clutter my gantt. So I splitted the task 13 times trying to leave 3
days per sub-split-task. Problem is that it's not very precise using the
mouse.
Is there a way to go back and edit the duration of all those sub-split-task
?
Thanks