Hi,
Well yes, you can do that, and you can enter remaining work for each of the
assignments, no problem.
My question was why stop Project from rescheduling the remaining work?
Note: if you enter reemaining work for both assignments, Project will not
recalculate that, but it may reschedule it (not the same thing)
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Mani said:
My objective is to be able to update the remaining work for each resource
for each task for each week. Every week I am given an update of the Actual
Work and sometimes, an adjustment of the remaining work. However, if I have
2 or more resources assigned to a task, I find that the work may not be
distributed correctly. For example a task that is estimated for 40 hours
may require Jim to be assigned for 30 and Jane for 10, but may actually be
20/20. The only way that I have figured so far to do this is by updating it
manually in a Time Scaled Task or Resource usage view... Any suggestions?