J
Jim Barnes
Hi -
It seems that the start and end dates for to do list tasks created in PWA
can not be edited. I am a PS administrator. I verified my permissions - I
have them all. I create a to-do list task for myself in PWA (visible to
everyone), and import the assignment into Outllok 2003 SP1 using the "Import
Assignment" functionality of PWA which was properly installed via the "Use
Outlook..." link in PWA. I edit the start and end dates in Outlook, and not
only do they not update PWA when the "Update Project Server" button is
clicked, they don't even show up in the tasks to update dialog. It seems
that the only field that gets updated is %complete. Further, I can not edit
the start and end dates in PWA either. Therefore, when I edit these dates in
Outlook, the old dates get imported on the next import. This essentially
makes the management of to do tasks in Outlook unusable. Any thoughts?
Thanks in advance.
Jim Barnes
It seems that the start and end dates for to do list tasks created in PWA
can not be edited. I am a PS administrator. I verified my permissions - I
have them all. I create a to-do list task for myself in PWA (visible to
everyone), and import the assignment into Outllok 2003 SP1 using the "Import
Assignment" functionality of PWA which was properly installed via the "Use
Outlook..." link in PWA. I edit the start and end dates in Outlook, and not
only do they not update PWA when the "Update Project Server" button is
clicked, they don't even show up in the tasks to update dialog. It seems
that the only field that gets updated is %complete. Further, I can not edit
the start and end dates in PWA either. Therefore, when I edit these dates in
Outlook, the old dates get imported on the next import. This essentially
makes the management of to do tasks in Outlook unusable. Any thoughts?
Thanks in advance.
Jim Barnes