Drew said:
If you double click on a task, you'll get the task information dialog box.
Within that dialog box is a tab for Predecessors. Is there a way to get a
Successors tab to display?
Drew,
No, not in the task information window. However you can always display
the Predecessor and Successor fields in any task view. Just right click
on the column heading where you want to insert new fields and then
select the fields you want.
You can also do a split window and show one of the PERT diagrams in the
lower pane. Network Diagram will show the relationship between two or
more selected tasks and the Relationship Diagram will show all
Predecessors and Successors of single or group of selected tasks.
Hope this helps.
John