EditSite and Project Server 2002 - DSN + MSProjectServerUser

P

Pete Smith

Hi,

we have already in our small company a Project Server 2002 with Hotfixes up
to March, 25th of 2003 applied. Now we want to setup a second instance with
EditSite. The following KB article describes the way

http://support.microsoft.com/default.aspx?scid=kb;EN-US;323021

Is it necessary to have the same DSN Name for both sites? Or should it be
two?
Is it necessary to have the same MSProjectServer and MSProjectServerUser for
both sites? Or is it better to have different?

Thanks in advance for you comment and
kind regards,

Pete
 
G

Gary L. Chefetz \(MVP\)

Pete:

You need to use a distinct DSN name. DO NOT USE the same DSN name. The 2002
EditSite tool might lure you into thinking this is OK, but it's not. As for
the MSProjectSeverUser and MSProjectUser, these can be the same or
different. Inasmuch as these are not exposed to anyone it's easier for the
administrator and less to document if they're the same.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top