Tommy Lovelace
Mornin' y'all, me again. A friend posed an interesting
question to me: Does the priority cell in a summary task
have any effect on the priority of its tasks when leveling?
We all know what happens when we link a predecessor or
assign a resource to a summary task. Does the summary
priority indicate a priority of all the tasks below it?
Should summary tasks be set to 0? If I set a summary
priority to 1000, will all of its tasks be passed over
when leveling?
Thanks...........Tommy