When re-reading especially this thread I have to admit some nerve is visble.
Sorry.
And yes, the word arrogance has come to surface when some people talk about
me.
It's not always the case, fortunately.
Greets,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
As I see it, levelling only delays tasks where an assigned resource it
overallocated, and the setting of Priority only applies when levelling - it
has no other purpose. As you shouldn't have any resources assigned to
summaries, then the priority setting is meaningless.
Mike Glen
MS Project MVP
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.