Effective dates for rates

T

TomL

MSP 2003 SP1 Server

We need to know where the effective dates and rates are stored in the
database. We are opening the Enterprise resource pool, double clicking on
the resource name, and putting in effective dates and rates. We have noticed
the changed rates do not seem to propogate to a project until it is opened
and saved again.

We assumed it was MSP_RESOURCE_RATES table but testing shows that is not the
case.

Does anybody know where these rates and dates are stored in the Server DB?
 