O
Oren
Hi All,
I am looking for command that will calculate the effective date of a predecessor which has lag or lead.
For example if I have a task that has a predecessor with finish date on December 7 and with lag of 3ed then the effective date of the predecessor is December 10 (in case of link type: finish to start).
Does anyone know what is the best way to write this?
Thanks
I am looking for command that will calculate the effective date of a predecessor which has lag or lead.
For example if I have a task that has a predecessor with finish date on December 7 and with lag of 3ed then the effective date of the predecessor is December 10 (in case of link type: finish to start).
Does anyone know what is the best way to write this?
Thanks