D
DS
Hi All.
I'm using MS-Project Pro 2003.
I'm in the "Resource Sheet" view and would like to get a calculation of the
actual effort days that my resources will be doing. I have added the
'Regular Work' column, which totals 'Work', but it seems to total the work
over the calendar schedule.
So, my 'Project Manager' who has tasks at the beginning of the project and
at the end of the project but in total does about 10 effort days of work, has
a 'Regular Work' total of 97 days (the duration of the project). The total
I'd like to see on the 'Resource Sheet' is the actual effort a resource is
committing to the project - in this case, the PM is spending 10 effort days
on the project (not 97).
Is there a column I can add (or a custom column) I can use to determine this
total?
Thanks.
DS
I'm using MS-Project Pro 2003.
I'm in the "Resource Sheet" view and would like to get a calculation of the
actual effort days that my resources will be doing. I have added the
'Regular Work' column, which totals 'Work', but it seems to total the work
over the calendar schedule.
So, my 'Project Manager' who has tasks at the beginning of the project and
at the end of the project but in total does about 10 effort days of work, has
a 'Regular Work' total of 97 days (the duration of the project). The total
I'd like to see on the 'Resource Sheet' is the actual effort a resource is
committing to the project - in this case, the PM is spending 10 effort days
on the project (not 97).
Is there a column I can add (or a custom column) I can use to determine this
total?
Thanks.
DS