Effort Driven Against Changing Resource Units

Joined
Mar 2, 2012
Messages
4
Reaction score
0
Dear all

The following is the definition in Program help of effort driven:

When a task is effort driven, Microsoft Office Project keeps the total task work at its current value, regardless of how many resources are assigned to the task.
When new resources are assigned, remaining work is distributed to them.

My question is:
Does the second sentence exclude changing a resource unit.
I mean if I have an effort driven resource using some resources; and I if I change the unit of one or more the assigned resources, will the task fix the total work acting as effort driven task or not?

Please advise me.
 