P
Pineflakes
I think I may be taking the the wrong approach to using Project, and I have
the feeling that there is probably a more efficient way to manage my projects
with it. In fact, I am a little worried that Project may not even be right
for my application. Please, any suggestions?
TYPE OF PROJECT: Planning a lengthy remodel of a six unit residential
building (many tasks of varying relationships) using very few resources (two
full-time workers paid hourly, and a few subcontractors, electricians,
deliveries, etc). I know the work for each task, but I want to track their
duration in order to know when to schedule subs or material deliveries.
PROBLEM: I can't find a useful way of assigning resources to the tasks
without creating messy over/underallocations and levelling issues up the
wazoo. I want to be able to assign each worker 100%, have them work an 8 or
10hr day (depending on the worker), and move directly on the the next task
once the first is completed, or automatically arrange their time to work on
another concurrent task if they should be available to do so.
WHAT I HAVE TRIED: Although I am rather new to Project, I have read the
Step-By-Step book and thoroughly investigated the Help topics. Again, I feel
that I understand the tools, features and concepts, but I am not applying
them correctly. I follow the basic project guide for entering a project's
details, starting by defining tasks, grouping them, and scheduling them, then
defining resources and assigning them. I have experimented with effort driven
scheduling and fixed units, and in my case, it seems that I should be using
fixed work since I know the man-hours for each task, but I am looking for the
task's revised duration after assigning resources. I end up manually
levelling everybody's work schedule, which is excruciatingly tedious for just
two workers since I have to make sure that I maintain the same amount of work
for each task without accidentally increasing it (as you know, even a fixed
work task can be manually changed). I want to control how many hours someone
spends on a task in a work day, not by a percentage of their available time.
For example, jack works a 10 hour day, and jill works an 8 hour day. They
are given three tasks to do: scraping (4 hrs of work), cleaning (4 hrs),
priming (12 hrs) and painting (12 hrs). All three tasks are start-to-finish
and cannot begin until the previous one is complete. With both of them
working together, scraping takes 2 hrs, cleaning takes 2 hrs, and then they
begin priming. After Jack and Jill prime for 4 hrs, Jill needs to clock out
and go home, leaving Jack to work another 2 hrs until he clocks out as well.
2 hrs of priming remains for the next day, when they both return to work and
finish priming together in an 1 hr. Then they are able to spend another 6 hrs
apiece painting.
In this example, I dont care whether Jack did more than 50% of the priming,
just as long as both he and Jill worked a full day, and didn't start painting
until all the priming was complete. How do I apply this to project? Am I
going about this all wrong? Does the solution have to do a different approach
to levelling resources, defining working times, work types, or assignment
units? It seems very simple but it has definitly been a black hole of time
and frustration for me, Aaghhhhh...
:O
the feeling that there is probably a more efficient way to manage my projects
with it. In fact, I am a little worried that Project may not even be right
for my application. Please, any suggestions?
TYPE OF PROJECT: Planning a lengthy remodel of a six unit residential
building (many tasks of varying relationships) using very few resources (two
full-time workers paid hourly, and a few subcontractors, electricians,
deliveries, etc). I know the work for each task, but I want to track their
duration in order to know when to schedule subs or material deliveries.
PROBLEM: I can't find a useful way of assigning resources to the tasks
without creating messy over/underallocations and levelling issues up the
wazoo. I want to be able to assign each worker 100%, have them work an 8 or
10hr day (depending on the worker), and move directly on the the next task
once the first is completed, or automatically arrange their time to work on
another concurrent task if they should be available to do so.
WHAT I HAVE TRIED: Although I am rather new to Project, I have read the
Step-By-Step book and thoroughly investigated the Help topics. Again, I feel
that I understand the tools, features and concepts, but I am not applying
them correctly. I follow the basic project guide for entering a project's
details, starting by defining tasks, grouping them, and scheduling them, then
defining resources and assigning them. I have experimented with effort driven
scheduling and fixed units, and in my case, it seems that I should be using
fixed work since I know the man-hours for each task, but I am looking for the
task's revised duration after assigning resources. I end up manually
levelling everybody's work schedule, which is excruciatingly tedious for just
two workers since I have to make sure that I maintain the same amount of work
for each task without accidentally increasing it (as you know, even a fixed
work task can be manually changed). I want to control how many hours someone
spends on a task in a work day, not by a percentage of their available time.
For example, jack works a 10 hour day, and jill works an 8 hour day. They
are given three tasks to do: scraping (4 hrs of work), cleaning (4 hrs),
priming (12 hrs) and painting (12 hrs). All three tasks are start-to-finish
and cannot begin until the previous one is complete. With both of them
working together, scraping takes 2 hrs, cleaning takes 2 hrs, and then they
begin priming. After Jack and Jill prime for 4 hrs, Jill needs to clock out
and go home, leaving Jack to work another 2 hrs until he clocks out as well.
2 hrs of priming remains for the next day, when they both return to work and
finish priming together in an 1 hr. Then they are able to spend another 6 hrs
apiece painting.
In this example, I dont care whether Jack did more than 50% of the priming,
just as long as both he and Jill worked a full day, and didn't start painting
until all the priming was complete. How do I apply this to project? Am I
going about this all wrong? Does the solution have to do a different approach
to levelling resources, defining working times, work types, or assignment
units? It seems very simple but it has definitly been a black hole of time
and frustration for me, Aaghhhhh...
:O