smck
for a fixed duration, effort driven task, with both resource 100%
availability, when one resource is assigned to a task the unit and work is
calculated by project.
When an additional resource is assigned to the same task, project reduces
the units of the first resource by 1/3 and assigns it to the second resource.
Why is the split not 50-50?
Any help is greatly appreciated.