F
Frank
I understand you can baseline a project plan and track schedule variances
once you start tracking with actuals, but it appears as though you
don't/can't baseline the "work" effort. In other words, if I baseline a task
for 40 hours, but it takes me 44 hours to complete the task, is there a way I
can record the 44 hours and identify this as a 4 hour work or effort variance
against my baseline?
once you start tracking with actuals, but it appears as though you
don't/can't baseline the "work" effort. In other words, if I baseline a task
for 40 hours, but it takes me 44 hours to complete the task, is there a way I
can record the 44 hours and identify this as a 4 hour work or effort variance
against my baseline?