M
matt
I am new to project and this one has me stumped. When we estimate times for
our tasks, we always list effort vs duration. Duration is actual working
days until it is finished, whereas effort is the amount of time we actually
work on it. For example, our automated testing takes 3 days to complete,
but only 1 hour to setup. If I enter 3 days into duration, MS Project shows
my resource as busy for those three days, when they are really only busy for
one hour. Almost all of our tasks have this lag (such as review the
documents, where we wait 5 days to get comments back). The important thing
to note is that for these tasks, throwing more resources at them will NOT
lessen the duration, our test automation will always take 3 days...
I want my resources to be allocated better, so that when someone starts, for
example, the automated test, they can spend the next 3 days (minus 1 hour)
working on another task. However, I still want to capture the 3 day delay so
I can get the correct end-date for the project.
My guess is that I need to change something in the realm of "Fixed
Effort/Fixed Duration" etc, but I have not figured this out. Right now all
of my tasks are "Fixed Duration" and "Effort Driven"
What is the preffered method to enter and represent this information?
our tasks, we always list effort vs duration. Duration is actual working
days until it is finished, whereas effort is the amount of time we actually
work on it. For example, our automated testing takes 3 days to complete,
but only 1 hour to setup. If I enter 3 days into duration, MS Project shows
my resource as busy for those three days, when they are really only busy for
one hour. Almost all of our tasks have this lag (such as review the
documents, where we wait 5 days to get comments back). The important thing
to note is that for these tasks, throwing more resources at them will NOT
lessen the duration, our test automation will always take 3 days...
I want my resources to be allocated better, so that when someone starts, for
example, the automated test, they can spend the next 3 days (minus 1 hour)
working on another task. However, I still want to capture the 3 day delay so
I can get the correct end-date for the project.
My guess is that I need to change something in the realm of "Fixed
Effort/Fixed Duration" etc, but I have not figured this out. Right now all
of my tasks are "Fixed Duration" and "Effort Driven"
What is the preffered method to enter and represent this information?