R
reuben
I am defining a new calendar called "Afternoon". Working hours are from 1:00
p.m.to 9:00 p.m.
Next I assign this calendar to my project in the Project information dialog
box and I set the default start hour at Menu/Tools/Options/Calendar at 1:00
p.m. and the default finish hour at 9:00 p.m. Working hours are changed to
48hrs a week.
So as far as I know all the initial configuratrions are made.
When I enter a task, let us say with a duration of 1 day, Project schedules
it correctly starting at 1:00 p.m.
However if I state a duration of 1ed, (1 elapsed day), task is scheduled to
start at 8:00 a.m. (seemingly it does not take into account the project
calendar when the duration is stated as elapsed)
Although I could make a walkaround forcing the task that has an elapsed
duration to have "Aftenoon" as its task calendar I find this rather clumsy to
do.
Although I know that elapsed would mean 24 hrs a day I want to start at the
same time than the other tasks (1:00 p.m.) of the project.
Anybody has any suggestion to correct this strange behaviour?
NOTE: I believe that this behaviour occurs in some files and not in others,
depending on the PC where you are working, but I did not find any difference
in the options dialog box of the different files.
p.m.to 9:00 p.m.
Next I assign this calendar to my project in the Project information dialog
box and I set the default start hour at Menu/Tools/Options/Calendar at 1:00
p.m. and the default finish hour at 9:00 p.m. Working hours are changed to
48hrs a week.
So as far as I know all the initial configuratrions are made.
When I enter a task, let us say with a duration of 1 day, Project schedules
it correctly starting at 1:00 p.m.
However if I state a duration of 1ed, (1 elapsed day), task is scheduled to
start at 8:00 a.m. (seemingly it does not take into account the project
calendar when the duration is stated as elapsed)
Although I could make a walkaround forcing the task that has an elapsed
duration to have "Aftenoon" as its task calendar I find this rather clumsy to
do.
Although I know that elapsed would mean 24 hrs a day I want to start at the
same time than the other tasks (1:00 p.m.) of the project.
Anybody has any suggestion to correct this strange behaviour?
NOTE: I believe that this behaviour occurs in some files and not in others,
depending on the PC where you are working, but I did not find any difference
in the options dialog box of the different files.