D
DavidC
I have a task which was originally set as an elapsed duration. Now I need to
change the duration to a duration under a specific calendar. Every time I
change the duration and calendar in task information, the duration keeps
reverting back to elapsed duration. I have checked the options box out but
that does not seem to have any feature to turn on or off.
Any ideas please
Regards
DavidC