D
DavidC
Hi,
All the commentary and documentation indicates that elapsed duration is
independant of the calendar settings. It is logical then that a task
starting on the 1st of the month and ending 2 elapsed months later, would
then finish on the 1st of the month two months hence. However, I have
noticed an oddity with this function. A task with an elpased time of 5
months and starting on the 8th of the month, actually ends on the 4th of the
month, effectively shortening up the time by 4 days. In reality I am not
overly concerned with this difference, but I have been quized as to why the
difference and have no answer.
Any thoughts please.
regards
DavidC
All the commentary and documentation indicates that elapsed duration is
independant of the calendar settings. It is logical then that a task
starting on the 1st of the month and ending 2 elapsed months later, would
then finish on the 1st of the month two months hence. However, I have
noticed an oddity with this function. A task with an elpased time of 5
months and starting on the 8th of the month, actually ends on the 4th of the
month, effectively shortening up the time by 4 days. In reality I am not
overly concerned with this difference, but I have been quized as to why the
difference and have no answer.
Any thoughts please.
regards
DavidC