I have a question on how to view in project plan the remaining work?
For a example....
A task has started at 20-3-2008
However until now (1st Oct 2008) only 80% of the work is completed.
Task type = Fixed work and should be set to 10 days (I do not know where I
can enter the Fixed work of 10 days as I can only enter the duration!)
This means that the remaining fixed work is 2 days.
If the resource unit is set to 50%, this would mean that the remaining
duration is 4 days as from today.
I would then like to see on my gantt chart that the finish date would be
Monday 6 October.
Is this possible in MS Project?
I have a question on how to view in project plan the remaining work?
For a example....
A task has started at 20-3-2008
However until now (1st Oct 2008) only 80% of the work is completed.
Task type = Fixed work and should be set to 10 days (I do not know where I
can enter the Fixed work of 10 days as I can only enter the duration!)
This means that the remaining fixed work is 2 days.
If the resource unit is set to 50%, this would mean that the remaining
duration is 4 days as from today.
I would then like to see on my gantt chart that the finish date would be
Monday 6 October.
Is this possible in MS Project?