L
lynne
Hi all
We have a standalone electronic timesheet system in this
organisation. I've been recruited to bring about a little order and
structure to the project management and I was keen to use Project
Server mainly for the Issue Log/Risk Register and Enterprise Resource
Pool functionality. Obviously people are not best pleased with the
idea of dual entry of their hours so using PWA to track their time is
going to be tricky!
Please can anyone offer an opinion about how I might go about
reconciling this?! I think we should be tracking resource time using
Project in some shape otherwise how can we see what's slipping etc?
Is it possible to take an export from Project, or from our Timesheet
system to share data between the two systems?
Thanks v much!
lynne
We have a standalone electronic timesheet system in this
organisation. I've been recruited to bring about a little order and
structure to the project management and I was keen to use Project
Server mainly for the Issue Log/Risk Register and Enterprise Resource
Pool functionality. Obviously people are not best pleased with the
idea of dual entry of their hours so using PWA to track their time is
going to be tricky!
Please can anyone offer an opinion about how I might go about
reconciling this?! I think we should be tracking resource time using
Project in some shape otherwise how can we see what's slipping etc?
Is it possible to take an export from Project, or from our Timesheet
system to share data between the two systems?