Cheryl said:
Hi Mike,
I am building a very large project in ver 2002. I would like to cut and
paste some of the task blocks that are duplicates. These block consist of a
summary task and job tasks. When I copy and paste these items, they take
indention under the task where they are copied.
Collapse the task above where you are pasting them and they will not be
indented.
If you copy and paste a collapsed summary task it will include all the sub
tasks so it is easy to copy the whole block. Try it and see.
When I try to outdent, Project promptly displays a scheduling conflict
error box. What is interesting is that the conflict is tied to the very
first task which is an overall summary task of the project.
This could be something else. Are there links to summary tasks? Try
eliminating them and see what happens.
In addition, I have discovered that I can only link 2 task at a time. I
can't select sequential task and have the links trickle down as I was able
to in ver 2000. Any ideas on this as well.
I can do it. Select them all and then click on the little link icon (looks
like a chain). Perhaps there are some hidden tasks in your project (is there
a filter on by any chance?)
-Jack