F
foon
Hi,
I have two questions for MS project 2003 web access and project
professional
1.compare start/ finish and actual start/ actual finish variance
For example, Project manager assign a task to team member which start
date on
2005-07-01 and finish date on 2005-07-05. However, the team login the
web access to update the task on 2005-07-08 (delay 3 days) and request
project manager to approval the request. Project manager get the email
notification from projectserver and login in web access to accept the
request, after approval the request, project would show start date on
2005-07-01 and finish date on 2005-07-05 (according to submitting
date, it should be 2005-07-08). I searched the reference book and
found the solution as project manager should key in the actual start
/actual finish date with project professional by using
tools->tracking->update task->key in actual start/finish date.
I think it should have more convenience way to handle this case,the
system record the submited date(2005-07-08) , if I can use this date
as actual complete date and then compare with finish date in
baseline(2005-07-05) that we can compare the task delay for 3 days.
2. Eamil alert to senior management when their staff have overdue task
Another example, I am a executive and 1 managers report to me. There
are 5 members of staff report to the manager. I want to get email
alert to me when any tasks assigned to those 5 members and the manger
are overdue. I tried to set up the resource break down structure and
using web access to config "Alert me about my resource on task and
status reports" but still did work.
Please note that I am not a project manager nor team member of the
project.
I search many reference books and internet resoure but no any better
solution
Any one can give me a halping hand to solve my problems?
Thak you very much
I have two questions for MS project 2003 web access and project
professional
1.compare start/ finish and actual start/ actual finish variance
For example, Project manager assign a task to team member which start
date on
2005-07-01 and finish date on 2005-07-05. However, the team login the
web access to update the task on 2005-07-08 (delay 3 days) and request
project manager to approval the request. Project manager get the email
notification from projectserver and login in web access to accept the
request, after approval the request, project would show start date on
2005-07-01 and finish date on 2005-07-05 (according to submitting
date, it should be 2005-07-08). I searched the reference book and
found the solution as project manager should key in the actual start
/actual finish date with project professional by using
tools->tracking->update task->key in actual start/finish date.
I think it should have more convenience way to handle this case,the
system record the submited date(2005-07-08) , if I can use this date
as actual complete date and then compare with finish date in
baseline(2005-07-05) that we can compare the task delay for 3 days.
2. Eamil alert to senior management when their staff have overdue task
Another example, I am a executive and 1 managers report to me. There
are 5 members of staff report to the manager. I want to get email
alert to me when any tasks assigned to those 5 members and the manger
are overdue. I tried to set up the resource break down structure and
using web access to config "Alert me about my resource on task and
status reports" but still did work.
Please note that I am not a project manager nor team member of the
project.
I search many reference books and internet resoure but no any better
solution
Any one can give me a halping hand to solve my problems?
Thak you very much