HI,
I'm having problems with email collaboration. When people respond
to the initial assignments, I try to update my project plan. Every
updates complains about constraints or dependancies being violated and
wont complete.
Having checked the plan, some of the tasks do not have date
constraints or dependant predecessors.
Has anybody else seen this problem or anything similar ?
On a related note, can you use email collaboration where the plan
contains links to another external (and unavailble) plan ?
Thanks for any help,
Paul
I'm having problems with email collaboration. When people respond
to the initial assignments, I try to update my project plan. Every
updates complains about constraints or dependancies being violated and
wont complete.
Having checked the plan, some of the tasks do not have date
constraints or dependant predecessors.
Has anybody else seen this problem or anything similar ?
On a related note, can you use email collaboration where the plan
contains links to another external (and unavailble) plan ?
Thanks for any help,
Paul