Hi all
We are using a project pro 2007 Server
I have a project plan that contains a work of 2 teams.
Each employee, reports about his progress via PWA.
Is it possible that another person (Not the project manager- the owner of
the project) will be empowered to accept or reject employee’s updates?
We do not want to use master project in this specific case
Best regards
 
P

Paul Conroy

Each task can have a different status manager who is responsible for
accepting updates. Each status manager needs PM rights on the project.

(to change status manager, add the column status manager to your plan in
proj pro)
 
M

Monika

This was useful to read as this is the type of thing we are trying to
accomplish right now with project professional 2003. I suspect that status
manager is new to 2007. Does anyone know how to assign someone (or more than
one person), other than the project owner as the person(s) to accept updates
for specific tasks?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top